STAGE 1 The site of the proposed Conservatory |
![]() |
STAGE 4 Concrete is poured into the trench to form the foundations. |
![]() |
STAGE 2 Construction work begins. The ground is excavated to a min of 600mm deep for footings. Excavation exposes an underground drainage pipe. |
![]() |
STAGE 5 The concrete is floated to form a level surface to build upon. |
|
STAGE 3 Additional steel mesh reinforcement is introduced, the concrete foundation to prevent the drainage pipe being crushed. An alternative method is to use concrete lintels over the pipe. |
![]() |
STAGE 6 The inner leaf of the cavity wall is built up to floor level. |